CLIENT: Acciona Industrial
SERVICES: Detailed Engineering
YEAR: 2018
COUNTRY: México
The project includes the development of two wind farms called PER I-IV and PER V, two new substations (34.5/400 kV) and the required transmission lines in 400 kV.
The new Wind Farm will have a total of 123 wind turbines of 3.6MW each, with a combined total installed power of 442.8MW.
The scope of INGENOR corresponds to the detailed engineering of the Energy Plant.